A $184,300 claim, checked.

Input: the subcontract and its schedule of rates, the payment claim, previous claims, the approved variation register. Output: three items for review, each with the page.

Input
Progress claim 7, electrical subcontractor
LineDescriptionQtyRateThis claim
1Rough-in, levels 1 to 33$18,200$54,600
2Cable trays, level 2240 m$92$22,080
3Switchboard relocation, variation1$14,850$14,850
4Distribution boards, level 14$2,100$8,400
5Lighting, level 11$84,370$84,370
Total this claim$184,300
Also read

Subcontract SC-018, 62 pages, schedule of rates p. 17. Claims 1 to 6. Variation register, 41 entries.

Sitemind found
3 items require review
$14,850

Switchboard relocation. Not found in the approved variation register. Raised in site meeting 14 as rejected pending approval.

Variation register, 41 entries, no match. Minutes 14, decision 2.
$8,400

Distribution boards, level 1. Four units claimed. Four units already claimed and certified in claim 5, line 4.

Claim 5, line 4, certified 28 July.
$92 / m

Cable tray rate differs from the schedule of rates. Schedule shows $84 / m. Difference on this claim: $1,920.

Subcontract SC-018, schedule of rates, p. 17.
$139,050

Lines 1 and 5 match the schedule, quantities and previous claims. Cleared for certification.

The QS or CA makes the decision. Sitemind certifies nothing.

What it checked

  • Claimed amounts against the schedule of rates
  • Quantities against previous claims
  • Cumulative totals and retention
  • Variations claimed against variations approved
  • Evidence attached, or missing
  • Arithmetic

What happens with low confidence

When a line cannot be matched with confidence, it is sent for review with the reason, not guessed. On a real deployment of the accounts clerk, 69 of 1,641 invoices went that way. See the figures.